I have a Pod-Point solo. I can see how to set the charge rate by moving the dip switches according to the table in the manual. It refers to load limiting to be set by commissioning over Wi-fi. How is this done. I can log connect to Pod-Point by using the new IP address once connected to home Wi-fi but only see option to select Wi-fi network nothing about adjusting settings. The feature I want to check and change if necessary is the load limiting feature that uses the ct input from your meter tails.
I don't believe that this is designed to be user or installer set, but instead set by PodPoint. It was also intended as a feature to allow the centralised control of EV loads which has never been implemented to my knowledge.
Try calling PodPoint.
 