As of 2 July 2024 these are the UK sites listed in the Ionity Tracker (and separately via @dparr59 excellent updates in the Charging Locations at Planning Stages thread) as in construction or indeed in planning (most distant announcement to most recent)

Frimley
Entered 571 days ago
(Due to be energised around 19 June 2024)

York
Entered 561 days ago
(complete awaiting energisation)

Singing Kettle
Entered 372 days ago

Leicester
Entered 349 days ago
02/10/23 - updated planning application with 12 additional charge points (6 x Alpitronic HYC dual-head units) to the original 12 x ABB
(complete awaiting energisation)

Ayr
Entered 244 days ago

Doncaster
Entered 228 days ago

(groundworks almost complete, posts in place)

Sheffield
Entered 225 days ago

(complete awaiting energisation)

Abergavenny
Entered 225 days ago

South Normanton
Entered 225 days ago

(complete awaiting energisation)

Dungannon (NI)
Entered 200 days ago

Dundee
Entered 194 days ago


Sunderland
Entered 105 days ago


Lancaster North
Entered 91 days ago

Edinburgh, Shawfair Business Park
Entered 75 days ago
09/04/24 - link. Due to open autumn 2024

Bristol - Village Hotel
Entered 26 days ago
Planning approved on 1 Feb 2024, P23/03488/F

Hull - Village Hotel
Entered 21 days ago
Planning approved on 18 April 2024, 23/03522/FULL

Warrington - Village Hotel
Entered 8 days ago
Planning approved on 2 May 2024
2023/01545/FUL

Birmingham Walsall - Village Hotel
Entered 8 days ago
Planning approved on 28 May 2024
23/1601

Coventry - Village Hotel
Entered 8 days ago
Planning approved on 15 April 2024
PL/2024/0000321/FUL

Manchester Cheadle - Village Hotel
Entered 7 days ago
Planning approved on 22 May 2024
DC/091638


Swansea - Village Hotel
Entered 5 days ago
Planning approved on 8 April 2024
2023/2626/FUL


Cambridge, expansion - additional 18 charge points
Due by end of 2024

Peterborough, expansion - additional 18 charge points
Due by end of 2024

Beaconsfield, expansion - battery system planned
TBC. See link

Wrexham, Ramada Hotel
APPROVED, P/2023/0278

Droitwich Spa
30/04/23 in planning, W/23/00687/FUL

Almondsbury
22/02/24 WITHDRAWN,
P23/02088/F

Cross Hands, Llanelli
20/03/24 WITHDRAWN, PL/06697

Haverfordwest
APPROVED, 23/0646/PA

Manchester, Eccles (M30 7EY)
25/01/24 in planning, PA/2023/0497

Southport
30/01/24 in planning, DC/2024/00197

Gloucester
28/03/24 in planning S.24/0598/FUL

Bristol (Eastgate)
APPROVED, 23/04014/F


Dartford, Doubletree Hilton
APPROVED, 24/00365/FUL


I will provisionally add the 33 new Village Hotels / Ionity sites below (in alphabetic order) as announced on 12 September. As more details become available I can update / edit this post.

Aberdeen - APPROVED, 240077/DPP

Basingstoke - APPROVED, 24/00361/FUL

Birmingham Dudley - APPROVED, 23/1606


Birmingham Walsall - APPROVED, 23/1601

Blackpool - APPROVED, 24/0024

Bournemouth - APPROVED, 7-2024-9177-EH

Bracknell - 12/04/24 in planning 24/00193/FUL

Bristol - APPROVED, P23/03488/F


Cardiff - 24/01/24 in planning, 24/00164/FUL

Chester St David's - 19/03/24 in planning, FUL/000203/24

Coventry - APPROVED, PL/2024/0000321/FUL

Edinburgh - 16/05/24 WITHDRAWN, 24/00133/FUL


Farnborough

Glasgow - 24/01/24 in planning, 24/00164/FUL

Hull - PERMITTED, 23/03522/FULL


Leeds North - REFUSED, 23/07573/FU, REFUSED again, 24/01878/FU

Leeds South - REFUSED, 24/00376/FU. REFUSED again, 24/01877/FU

Liverpool - 15/03/24 in planning 24/00127/FUL

London Watford - PERMITTED, 24/0224/FUL


Maidstone - PERMITTED, 24/501357/FULL

Manchester Ashton

Manchester Bury
- 26/02/24 in planning 23/01367/FUL

Manchester Cheadle - APPROVED DC/091638

Manchester Hyde - 19/12/23 in planning, 23/01106/FUL

Newcastle - 16/02/24 in planning 24/00200/FUL

Nottingham - 19/01/24 in planning, 24/00034/FUL


Portsmouth

Solihull - WITHDRAWN, PL/2023/02638/PPFL

Southampton Eastleigh

Swansea - APPROVED,
2023/2626/FUL

Swindon - 28/03/24 in planning, S/24/0368

Warrington - APPROVED, 2023/01545/FUL

Wirral - 16/02/24 in planning, APP/24/00220


[edits to OP in red]
 
#3 ·
Indeed. There will be 65 Ionity sites in the UK total - the existing 22, the 10 variously in construction and the 33 new Village Hotels sites. The rough timetable, if it can be believed, for the Village Hotels sites (compared to the average Ionity construction time in the UK), is very aggressive indeed.

All these sites to be operational by 2024.
 
#16 · (Edited)
View attachment 182437

Village hotels: There's some useful locations for long distance travelling and will help fill the gap before MSAs all have decent charging hubs (2035?).
The majority of those village hotel locations are already fairly well served by charging hubs; there is no revolution here but it'll help to provide extra competition and capacity for more new cars. The Portsmouth one is out on a limb with no other hubs but not sure about any of the others (edit, maybe Blackpool too?)
The new Ionity site that I'm most interested in is Singing Kettle.
 
#19 ·
Well, yes, though there are some decent areas around Blackpool and the Cricket ground in Stanley park is decent for the occasional Lancashire match (which happens to be by the village hotel).
 
#21 ·
I will provisionally add the 33 new Village Hotels / Ionity sites below (in alphabetic order) as announced on 12 September. As more details become available I can update / edit this post.
Swansea
Swansea Village Hotel will effectively create a secondary motorway services (though comfortably off the motorway) serving the East side which would be great.
You have the huge Gridserve set up to the West and then you'd have this on the East with a handy Starbucks right next to it (from memory, I think that's still there?).
 
#22 ·
Pity Fort William is not on that list. It was on a previous thread.

I use ionity all the time as I got a year of it at 25p per kWh and now on 31p on Elli.

I have used them for travelling over to Norway and this weekend it’s all I need to get to, South wales and back To scotland. Going to try out the 12 charger Starbucks at Carlisle.
 
#24 ·
Pity Fort William is not on that list. It was on a previous thread.

I use ionity all the time as I got a year of it at 25p per kWh and now on 31p on Elli.

I have used them for travelling over to Norway and this weekend it’s all I need to get to, South wales and back To scotland. Going to try out the 12 charger Starbucks at Carlisle.
The list in the OP's post is the currently in-construction sites from Ionity own maps, and the announced sites for Village Hotels. It doesnt include planning applications, which I'm assuming hasnt been removed or rejected at Fort William.
 
#25 ·
As far as I know fort William is still going ahead

 
#28 ·
As far as I know fort William is still going ahead

They better crack on, Tesla just opened up their 6 units at Fort William today to non-Tesla's (amongst also Inverness and Eurocentral). Get the bagpipes ooot 😎
 
#26 ·
I just hope they are putting in at least 8 and hopefully 12+ at each site. A downside of being at a Village Hotel (there is one close by to me in Cardiff) is that there are often gyms/meetings rooms, swimming pools, cafes, restaurants and of course hotel rooms, so I envisage people just plugging in and buggering off for half a day. I hope they have proper overstay charges like Tesla. And I also suspect you will get ICE'ing as well at busier times. Time will tell.
Now I have lost my cheap Ionity deal via Hyundai (25p/kWh) after 2 years, the Ionity price has now gone up to 74p/kWh. OUCH!
Even with the Hyundai based new Ionity contract offer which is 15p/kWh discount which would make it 59p/kWh. But at a cost of £6.99/month. That is a big jump from 25p/kWh.
I am banking on Tesla fitting a lot more of their V4 chargers all over the place for me to use!
 
#33 ·
There was talk recently of Ionity Beaconsfield getting an on site battery to support the grid connection. I rarely saw over 90kw there when I would expect 150kw.
but a mate stopped there in his Taycan last week and got 270kw. Maybe the battery is installed.


As for Blackpool, i was up there in August. Stayed at the Hampton Hilton. Fuuse AC charging in the car park at only 35p kWh. Tram stop right outside.
 
#36 ·
There was talk recently of Ionity Beaconsfield getting an on site battery to support the grid connection. I rarely saw over 90kw there when I would expect 150kw.
but a mate stopped there in his Taycan last week and got 270kw. Maybe the battery is installed.


As for Blackpool, i was up there in August. Stayed at the Hampton Hilton. Fuuse AC charging in the car park at only 35p kWh. Tram stop right outside.
Just stopped at Beaconsfield to charge. Ionity was full so went to Gridserve. Failed after a few percent so moved to the free charger on ionity. 4 cars charging at 67kw (including a Taycan) and 2 in the high 90s at 13kw. No battery then.

Three cars waiting as well.
 
#43 ·
Once the site is listed by them as ‘in construction’ it’s already had all planning approvals done and dusted.

So really down to them for site construction / groundworks etc. and of course DNO / grid conn. from that point forward. They’re probably not going to bother too deep with DNO until they get the planning sorted. So I’d imagine the construction delays are really down to the grid conn and how that’s managed and delivered. Challenging no doubt, as with any operator, some of whom grumble more publicly about it.